Understand how to apply Engineering Change Management (ECM) in engineering projects, from ECR through approval, impact assessment, implementation, configuration control, and traceability.

Check it out!

Engineering Change Management (ECM) is the process used to identify, record, analyze, decide, implement, and verify changes affecting project engineering. Its purpose is to prevent changes to requirements, drawings, specifications, equipment, interfaces, or execution methods from being incorporated informally without a complete assessment of technical, safety, schedule, cost, contractual, documentation, and operational impacts.

In this article, ECM means Engineering Change Management, or engineering change management. The acronym does not refer to Enterprise Content Management or organizational change management. The focus is on technical control of changes that modify configuration, baselines, or engineering-project deliverables.

A consistent ECM process connects engineering, Project Controls, procurement, contracts, construction, commissioning, and operations. It turns a need for change into a traceable decision: the change is formalized through a request, analyzed by affected disciplines, submitted to the competent authority, converted into an authorized instruction, propagated to documents, and verified before closure.

What Is Engineering Change Management (ECM) in Engineering Projects

Engineering Change Management is a technical-governance discipline that controls changes during project development and implementation. Its scope begins when a new condition, incompatibility, improvement opportunity, or additional requirement may modify the approved solution. The process ends only when the decision has been implemented, verified, documented, and reflected in the current configuration.

A change may appear small in the document that originated it and still produce systemic effects. Changing equipment power may require revisions to electrical supply, protection, cables, ventilation, structure, automation, signal lists, budget, purchase orders, schedule, tests, and operating procedures. ECM exists to identify these dependencies before the change is released for implementation.

ECM, Integrated Change Control, Configuration, and Documents

ConceptMain functionEngineering application
Engineering Change Management — ECMControl the complete engineering-change lifecycleRequirements, solution, interfaces, equipment, execution, and final configuration
Integrated change controlEvaluate changes affecting the plan and baselinesScope, schedule, cost, quality, risks, resources, and contracts
Configuration managementKeep functional and physical characteristics under controlTechnical baselines, configuration items, versions, and approved state
Document controlManage issue, revision, approval, and distributionDrawings, design reports, specifications, lists, and records
Contractual change managementFormalize consequences between the partiesScope, price, schedule, conditions, and responsibilities

ECM acts as a bridge among these systems. An approved technical change needs to update the configuration; when it affects the plan, it goes through integrated change control; when it changes contractual obligations, it requires the mechanism established in the contract; and in every case, it must be distributed through controlled documents.

ECR, ECN, ECO, and CCB

Terminology varies among organizations. The acronyms below are common, but the project procedure should define the terms adopted.

Acronym or termMeaningFunction
ECR — Engineering Change RequestEngineering change requestRecord need, justification, and initial assessment
ECN — Engineering Change NoticeEngineering change noticeCommunicate an authorized or pending change
ECO — Engineering Change OrderEngineering change orderTechnically authorize implementation
CCB — Change Control BoardChange control boardEvaluate and decide according to authority level
Change RegisterChange registerConsolidate status, decisions, owners, impacts, and deadlines
Configuration BaselineConfiguration baselineRepresent the approved set of characteristics
Change OrderContractual changeFormalize effects on obligations, price, schedule, or conditions

ECR and ECO do not need to be separate forms in small projects. The essential requirement is to separate request, analyze, authorize, implement and verify, while preserving history, responsibilities, and evidence.

Why ECM Is Critical in Engineering Projects

Engineering projects are multidisciplinary and progressive. Definition evolves from feasibility through detailed design, while successive decisions commit resources, contracts, equipment, and construction. The later a change occurs, the greater the number of elements that tend to depend on the previous configuration.

In early phases, a change may require only a new analysis. After procurement, it may require renegotiation with suppliers. During execution, it may cause rework, loss of productivity, or stoppage. Near commissioning, it may invalidate tests and acceptance evidence. This relationship should be considered together with the project lifecycle.

Changes Need to Be Controlled, Not Avoided.

The value of ECM lies in allowing necessary changes to proceed with proportional analysis, defined authority, complete communication, and implementation verification.

Understand How the Lifecycle Changes the Cost and Risk of Changes

Which Changes Should Enter the ECM Process

Any change capable of modifying an approved requirement, expected performance, technical solution, interface, configuration item, baseline, safety condition, contractual obligation, or information used to manufacture, procure, install, test, operate, or maintain the system should enter ECM.

Not every editorial correction requires multidisciplinary analysis. However, classifying a change as “just a drawing revision” without examining its content is a mistake. The criterion should be the potential effect of the change, not the document format.

Sources of Engineering Changes

Changes may originate from the owner, designer, supplier, contractor, operator, oversight team, regulatory authority, or field condition. Major triggers include:

  • modification of owner or user requirements;
  • correction of error, omission, conflict, or incompatibility;
  • need identified through risk or safety analysis;
  • standards, regulatory, or licensing change;
  • equipment unavailability or substitution;
  • value engineering or constructability improvement;
  • field condition differing from design information;
  • interference among disciplines or systems;
  • change of supplier, technology, material, or method;
  • result of inspection, FAT, SAT, or commissioning;
  • schedule, budget, logistics, or operational constraint;
  • RFI, nonconformity, or pending item whose resolution changes the engineering.

An RFI may clarify without changing anything; a nonconformity may be corrected in accordance with the design; a risk may be treated without changing the baseline. When the response modifies the approved solution, the case should be linked to a controlled change.

Classification by Nature

ClassExampleAnalyses normally required
RequirementNew capacity, availability, or operating conditionBusiness case, architecture, validation, and acceptance
TechnicalChange in sizing, topology, or specificationCalculations, compatibility, safety, and performance
ConfigurationSubstitution of component, material, firmware, or modelEquivalence, interoperability, documentation, and maintenance
InterfaceChange in boundaries among disciplines or suppliersResponsibilities, connections, data, sequence, and tests
ConstructionChange in method, access, sequence, or assemblyConstructability, safety, resources, schedule, and quality
RegulatoryNew legal, standards, or environmental requirementCompliance, licenses, and evidence
ContractualAddition, removal, or modification of an obligationScope, price, schedule, risks, and notices
OperationalChange in operation, maintenance, or contingencyProcedures, training, availability, and assets
EmergencyImmediate action to control severe riskExceptional authorization, temporary control, and regularization

The same change may belong to several classes. Equipment substitution may affect interfaces, electrical consumption, heat dissipation, protocol, schedule, cost, warranty, and spares.

Change, Deviation, Nonconformity, and Revision

RecordCharacteristicWhen to trigger ECM
ChangeProposes changing an approved condition or baselineAlways
DeviationRecords departure from a requirement or planWhen its acceptance changes the approved configuration
NonconformityShows noncompliance with a requirementWhen disposition is not simply correction according to the baseline
RFIRequests clarificationWhen the response introduces a technical change
Pending itemRecords an open action or decisionWhen the solution modifies a requirement or configuration
Document revisionNew document versionWhen technical content is modified
RedlineRecords a proposed or executed conditionWhen it differs from the released document
Editorial correctionAdjustment with no technical effectNormally document control only

The distinction avoids bureaucratizing simple corrections while preventing relevant changes from being executed as clarifications or field adjustments.

Materiality and Project Phase

A change is material when it affects function, safety, compliance, interfaces, budget, critical path, committed equipment, executed work, testing, operations, or released documents.

PhasePredominant impactRecommended control
Feasibility and FELAssumptions, benefits, CAPEX, and risksUpdate business case and continuation decision
Conceptual DesignArchitecture, capacity, and interfacesCompare alternatives and selection criteria
FEED and Basic DesignRequirements, bases, specifications, and estimatesMultidisciplinary analysis and contracting maturity
Detailed DesignCalculations, details, lists, and coordinationStrict configuration control
ProcurementRequisitions, equipment, manufacturing, and deliveryAssess commitments and suppliers
ExecutionField, method, rework, safety, and productivityApprove before execution, except in emergencies
CommissioningTests, logic, performance, and evidenceRevalidate procedures and criteria
CloseoutActual configuration and final documentationUpdate As-Built, manuals, and asset records

The content on FEED, Basic Design and Detailed Design detail maturity evolution. ECM should prevent late decisions from being treated as if the project were still in the conceptual phase.

The Impact of Change Increases as the Project Becomes More Committed.

A still-conceptual change may require only new analysis; after contracting, manufacturing, or execution, the same decision may generate rework, replanning, renegotiation, and repeated testing.

Explore How Project Controls Measures Schedule, Cost, and Baseline Impacts

How the Request, Analysis, and Approval Flow Works

An ECM workflow needs to be formal enough to protect configuration and agile enough not to paralyze decisions. The recommended structure separates identification, recording, triage, integrated analysis, decision, authorization, implementation, and verification.

ECR: Identification and Recording

The need should be recorded before being incorporated into documents or construction. The ECR receives a unique code and links origin, requester, date, discipline, affected item, current condition, proposal, justification, urgency, and evidence.

Coding may reflect project, system, and sequence, such as PRJ-ECM-ECR-001. The code remains stable even if the change results in several documents or orders.

Triage and Alternatives

Triage confirms whether the case is a change, checks for duplication, defines priority, identifies disciplines, and selects the workflow. It may return an incomplete request or link it to an RFI, nonconformity, risk, contract, or pending item.

Relevant changes should not reach decision with only one assumed solution. Engineering should compare alternatives, including maintaining the current configuration, explicitly stating requirements met, risks, interfaces, cost, schedule, reversibility, and operational implications.

Integrated Impact Analysis

Each affected area records its assessment in a common basis. The coordinator consolidates contributions, highlights disagreements, and confirms whether interfaces were consulted. The RACI matrix defines participation but does not replace technical, financial, or contractual authority levels.

Decision and ECO

Decisions should be standardized: approved, approved with conditions, rejected, returned, suspended, deferred to a future phase, or canceled. The record should identify the version analyzed, participants, justification, and conditions.

Approval needs to be converted into an executable instruction. The ECO — Engineering Change Order — defines the authorized alternative, affected documents and items, owners, deadline, restrictions, verifications, effects on baselines, and linkage to any contractual change order.

Implementation and Closure

The status “approved” does not mean “implemented.” Implementation includes engineering revision, document issue, procurement, manufacturing, construction, parameterization, testing, and communication. When several packages are involved, the change may be decomposed and linked to the WBS.

Closure confirms current documents, withdrawal of obsolete versions, consistency of materials and equipment, completion of tests, updates to contracts and baselines, As-Built documentation, manuals, asset records, and communication to stakeholders.

Minimum ECR Checklist

  • ☐ Unique identification and date
  • ☐ Requester, origin, and owner
  • ☐ Current condition
  • ☐ Proposed change
  • ☐ Justification and expected benefit
  • ☐ Affected requirements and items
  • ☐ Related documents, contracts, and assets
  • ☐ Disciplines and interfaces involved
  • ☐ Criticality and urgency
  • ☐ Alternatives considered
  • ☐ Preliminary impacts
  • ☐ Attachments and evidence
  • ☐ Required decision and deadline

Emergency Changes

An emergency may justify immediate action when there is severe risk to people, the environment, the asset, continuity, or compliance. This does not eliminate ECM; it only changes the sequence. The emergency workflow should define authority, intervention limits, temporary controls, preservation of evidence, regularization deadline, verification, and update of the final configuration.

Approval Does Not Mean Closure.

The change can be closed only when current documents, the executed condition, tests, records, and communication to operations are consistent with the authorized decision.

See How the As-Built Consolidates the Configuration Actually Implemented

How to Assess Technical, Contractual, Schedule, and Cost Impacts

Impact analysis is the core of ECM. Deciding solely on direct cost can overlook incompatibilities, rework, delays, productivity loss, additional testing, contractual obligations, and operational consequences.

DimensionMain questionsTypical evidence
RequirementsAre function, capacity, and acceptance still satisfied?Requirements matrix, Basis of Design, and calculations
SafetyDoes the change introduce risk or alter compliance?Risk analysis, technical opinions, and approvals
EngineeringWhich disciplines, calculations, and interfaces change?Document list and multidisciplinary analysis
ConstructabilityCan the solution be executed under the available conditions?Method, field conditions, resources, and sequence
ProcurementDoes it affect supplier, purchase order, manufacturing, or logistics?Requisitions, orders, and promised dates
ScheduleDoes it affect logic, critical path, float, or milestones?Schedule, fragnet, and path analysis
CostWhat direct, indirect, and lifecycle costs arise?Estimate, quotations, and forecast
ContractDoes it change obligations, price, schedule, or risk?Contract, notices, and administrative opinion
TestingDoes it invalidate inspections, FAT, SAT, or acceptance?ITP, protocols, and records
OperationsDoes it affect training, maintenance, or continuity?Manuals and operational analysis
ConfigurationWhich baselines and documents must be updated?Propagation matrix and master list
RisksWhich risks are introduced or removed?Risk register and responses

The risk management in engineering projects must be updated. Risk and change are not synonymous: risk is uncertainty; change is a proposed or actual alteration. A change can be a response to risk and can also create new risks.

Schedule, Cost, and Cumulative Impact

Schedule analysis should insert the change into the current schedule and evaluate logic, resources, procurement, float, critical path, milestones, mitigation, and acceleration. The physical-financial schedule shows why schedule, measurement, and cost cannot be assessed separately.

The estimate should state scope, assumptions, exclusions, base date, sources, and degree of definition. It may include engineering, materials, order cancellations, manufacturing, logistics, labor, supervision, mobilization, rework, testing, extended presence, productivity, and lifecycle costs.

Direct impact belongs to the changed work. Indirect impact results from effects on other activities. Cumulative impact arises when several changes produce a combined effect that cannot be attributed to a single change. Successive small changes can fragment work fronts, reduce productivity, and consume engineering capacity.

Technical Change, Change Order, and Claim

An engineering change is not automatically a contractual change. First the technical need is identified and analyzed; then responsibilities are verified, effects are quantified, and the contractual mechanism is applied.

When there is agreement, the effect may be formalized through a change order, amendment, work order, or equivalent instrument. When there is disagreement over entitlement, responsibility, price, or schedule, the case may evolve into a claim. The content on EPC and EPCM helps explain risk allocation.

Technical approval does not replace commercial authorization, and commercial approval does not dispense with technical validation.

When to Revise the Baseline

Not every change justifies rebaselining. Changing the reference simply to eliminate variances destroys performance history. Revision is appropriate when a formally authorized change makes the previous baseline inadequate by changing scope, budget, schedule, milestones, or strategy.

History must be preserved. The system distinguishes the original baseline, authorized revisions, current schedule, and forecast. The Earned Value Management depends on this discipline.

Rebaselining Requires Formal Decision and Preserved History.

A new baseline should reflect an authorized change that materially changed scope, schedule, budget, or strategy, without erasing the original reference or turning a variance into planned performance.

Understand How Earned Value Management Depends on Reliable Baselines

How to Apply Change Control in Agile or Hybrid Management

An agile or hybrid approach does not eliminate Engineering Change Management. What changes is the speed of discovering, qualifying, and routing the change. Ideas, pending items, emerging requirements, and alternatives can be refined in short cycles; however, when a change affects a baseline, approved requirement, configuration, contract, safety, cost, or schedule, it must pass through the corresponding formal governance.

PMBOK Guide 8th Edition treats tailoring and hybrid approaches as part of the normal management architecture. For Engineering, this means separating two layers: an adaptive layer for exploring and qualifying work not yet authorized, and a formal decision layer for changes that alter approved commitments. This separation is detailed in the architecture of agile and hybrid management of Engineering projects.

SituationRecommended treatmentRequired control
technical idea or hypothesisrefinement, study, or backlogrecord and owner
clarification with no material impactfast operational flowdocument traceability
change affecting an interface or requirementintegrated impact analysisECR/CCB or equivalent workflow
change in baseline, contract, or budgetformal decision before executionchange control, authority level, and history
field emergencypredefined exceptional flowauthority, limit, evidence, and subsequent regularization

A Change Backlog Is Not Change Authorization

A project backlog can organize requests, alternatives, studies, and pending items before a decision. It does not replace the ECR, CCB, change order, or any formal mechanism required by the contract and governance. An item may be prioritized in the backlog and still remain not authorized for implementation.

This separation avoids one of the main risks of superficial agile adoption: confusing the ability to react quickly with permission to change an approved reference without impact analysis.

Hybrid Change Control Should Accelerate Triage, Not Reduce Rigor

The gain from a hybrid approach lies in reducing idle time. Visual management, Kanban, classes of service, aging, and short cadences can make pending changes more visible and accelerate information gathering. Formal decision-making remains proportional to materiality: a simple document correction does not need to follow the same process as a change affecting CAPEX, contractual schedule, functional safety, or field configuration.

For this reason, hybrid ECM combines flow management with change governance. The first reduces queues and aging; the second protects the baseline, responsibility, and traceability.

How to Control Configuration, Documents, and Implementation

ECM produces results only when the decision reaches all affected elements. The change does not end in the CCB minutes or with issuance of a drawing. Requirements, documents, materials, equipment, software, parameters, construction, and operational records all need to be controlled.

Configuration Items and Baselines

A configuration item is a controlled element whose characteristics need to be identified, approved, and traceable. It may be a requirement, system, equipment, component, software, logic, parameter, interface, document, model, or installed assembly.

The configuration baseline represents the approved state. It may be functional, design, manufacturing, construction, or As-Built. The procedure defines when it is established, who approves it, and which changes require formal control.

Document Propagation Matrix

Changed elementPotentially affected documents
Functional requirementURS, OPR, Basis of Design, requirements matrix, and acceptance
Capacity or loadCalculations, balances, diagrams, lists, and specifications
EquipmentDatasheet, requisition, materials, drawings, and maintenance
LayoutDrawings, sections, supports, access, and safety
Electrical supplySingle-line diagram, demand, cables, protection, and selectivity
AutomationNarrative, I/O, cause and effect, software, and tests
CommunicationsArchitecture, addressing, protocols, and cybersecurity
Execution methodProcedure, risk, planning, and inspection
Test criterionITP, FAT, SAT, commissioning, and acceptance
Operating conditionManual, training, maintenance, and asset record

In BIM projects, the ISO 19650 series supports information management, but ECM also applies without BIM.

Information States and Implementation Package

The system should distinguish states such as drafting, review, approved, released for procurement, manufacturing or construction, canceled, superseded, and As-Built. There must be no doubt about which version is valid for each purpose.

Relevant changes should generate a package containing the ECO, drawings, analysis memorandum, method, safety, materials, responsibilities, implementation window, inspection, testing, rollback where applicable, and completion criteria.

Field, Redlines, and Commissioning

The field team should not alter the solution for convenience without authorization. Redlines document a proposed or executed condition but do not constitute automatic approval. The final configuration needs to be consolidated in the As-Built.

Changes after testing may invalidate evidence. The commissioning should indicate which verifications need to be repeated and how the change affects technical acceptance.

Closure should distinguish physical, documentary, technical, contractual completion, and communication to operations.

The Authorized Configuration Must Reach the Field.

Drawings, lists, parameters, equipment, software, procedures, and test records need to represent the same approved solution; discrepancies between documents and installation keep the change open.

Explore How Commissioning Verifies Changes Before Acceptance

How to Structure ECM Governance, Metrics, and Audit

Governance defines policy, roles, authority levels, criteria, workflow, information, and oversight. ECM should be integrated with processes and governance, rather than operating as a parallel register disconnected from documents, schedule, costs, and contracts.

Policy, CCB, and Authority Levels

The policy establishes principles and responsibilities; the procedure describes types, materiality, urgency, status, documentation, roles, authority levels, deadlines, CCB, integrations, rebaselining, emergencies, metrics, and audit.

The CCB evaluates changes above delegated authority levels or with relevant multidisciplinary impact. It may include the owner, manager, engineering, Project Controls, contracts, procurement, construction, commissioning, operations, safety, and quality. The matrix should indicate who recommends, who decides, and who is consulted.

Authority levels may consider safety, requirements, value, schedule, critical path, disciplines, contracts, shutdown, reversibility, and operational exposure. A safety or compliance change should not be simplified merely because it has low cost.

Recommended Roles

RoleMain responsibility
RequesterRecord need and initial information
ECM CoordinatorManage workflow, deadlines, and integration
Technical LeadDevelop alternatives and consolidate engineering
Affected disciplinesEvaluate interfaces and consequences
Project ControlsAnalyze schedule, cost, baseline, and forecast
ProcurementEvaluate suppliers, orders, and logistics
ContractsVerify obligations, change orders, and claims
ConstructionEvaluate field conditions, method, safety, and rework
CommissioningEvaluate tests and acceptance criteria
OperationsEvaluate maintenance, training, and assets
CCB or authorityApprove, reject, or impose conditions
VerifierConfirm implementation and closure

In projects with Owner’s Engineering, the role may include independent analysis, impact consolidation, evidence verification, and support for owner decisions without replacing the responsibilities of designers, suppliers, and contractors.

Metrics

MetricWhat it reveals
Open changes by statusVolume and bottlenecks
Backlog ageRisk of delayed decisions
Time from ECR to decisionAnalysis efficiency
Time from approval to implementationExecution capacity
Returned requestsInput quality
Emergency changesExposure and planning maturity
Unauthorized changesSerious control failure
Cost and schedule impactCumulative consequence
Origin and disciplineSources of instability
ReopeningImplementation quality
Documentation pendingConfiguration discrepancy
Recurring causesEffectiveness of lessons learned

Audit, Errors, and Maturity

The audit should make it possible to reconstruct origin, baseline, analysis, decision, instruction, revisions, execution, tests, impacts, and closure. Independent assurance is useful for critical changes, significant rebaselining, disputes, or changes close to acceptance.

Recurring errors include executing before approval, analyzing only the originating discipline, ignoring procurement and operations, estimating only direct cost, changing the baseline to eliminate variance, closing without field verification, and failing to update As-Built documentation or manuals.

LevelCharacteristics
ReactiveChanges identified after execution and scattered records
ControlledForm, register, and basic approval
IntegratedEngineering, schedule, cost, risk, contracts, and configuration connected
ManagedAuthority levels, metrics, audit, and cause analysis
OptimizedHistorical data, prevention, automation, and continuous improvement

Implementation can start simply as long as essential controls are preserved. A complex form does not compensate for undefined authority or lack of verification. Recurring causes should feed lessons learned.

Mature ECM Integrates Engineering, Controls, and Governance.

Maturity lies not in form complexity, but in the ability to relate technical decisions, impacts, responsibilities, baselines, contracts, implementation, and closure evidence.

Learn about A3A Engenharia’s Owner’s Engineering Services

Technical References

[1] INTERNATIONAL ORGANIZATION FOR STANDARDIZATION. ISO 21500:2021 — Project, programme and portfolio management — Context and concepts.

[2] INTERNATIONAL ORGANIZATION FOR STANDARDIZATION. ISO 21502:2020 — Project, programme and portfolio management — Guidance on project management.

[3] INTERNATIONAL ORGANIZATION FOR STANDARDIZATION. ISO 21505:2017 — Project, programme and portfolio management — Guidance on governance.

[4] PROJECT MANAGEMENT INSTITUTE. A Guide to the Project Management Body of Knowledge — PMBOK Guide. 8. ed.

[5] AACE INTERNATIONAL. Recommended Practice 10S-90: Cost Engineering Terminology.

[6] AACE INTERNATIONAL. Recommended Practice 39R-06: Project Planning as Applied in Engineering and Construction for Capital Projects.

[7] INTERNATIONAL ORGANIZATION FOR STANDARDIZATION. ISO 19650-1:2018 — Information management using BIM.

[8] FIDIC. Conditions of Contract for EPC/Turnkey Projects. 2. ed. Silver Book, 2017.

[9] FIDIC. Client/Consultant Model Services Agreement. 5. ed. White Book, 2017.

Frequently Asked Questions
What Is Engineering Change Management (ECM)?

It is the process of identifying, recording, analyzing, approving, implementing, and verifying changes affecting requirements, configuration, documents, equipment, interfaces, or execution of an engineering project.

What Is the Difference Between ECR and ECO?

ECR is the request that describes and justifies the change. ECO is the authorization to implement the approved alternative. Terminology varies, but requesting and authorizing should remain separate.

What Is a CCB in Engineering Projects?

CCB is the committee or governance body that evaluates relevant changes and recommends, approves, conditions, or rejects their implementation according to authority levels.

Does Every Drawing Revision Need to Go Through ECM?

No. Editorial corrections may remain within document control. Revisions that modify requirements, solution, interfaces, configuration, manufacturing, construction, testing, or operations should be evaluated through ECM.

Is ECM the Same as a Change Order?

No. ECM controls the technical change and its impacts. A change order is a contractual instrument when the change alters obligations, price, schedule, or conditions.

How Should Emergency Changes Be Handled?

Through an exceptional workflow defining authority, intervention limits, temporary controls, evidence, regularization deadline, subsequent verification, and configuration update.

When Does a Change Require Rebaselining?

When an authorized change materially alters scope, budget, schedule, milestones, or strategy and makes the previous baseline inadequate. History should be preserved.

Is Specific ECM Software Required?

No. The process can begin with controlled records. Complex projects benefit from platforms that relate changes to requirements, documents, schedules, costs, contracts, risks, and configuration.

Complementary Technical Materials

Whitepapers

Technical Articles

Technical Guides

Related Services

Related Solutions